Projects

Projects

2018 East Livingston Street Improvements Project

PAB Construction Co. has completed the Livingston St. project, phases 1 and 2 with the exception of a final punchlist.  Final punchlist will include final grading and seeding in the tree lawn areas.  This is scheduled to be completed in spring 2020.

2020 Street Resurfacing Project

The street resurfacing project is currently in the planning and design stage.  Access Engineering Solutions and the City of Celina expect to put this project out for bid in late May or early June with construction beginning after July 1, 2020.

Streets considered for resurfacing are: Irmscher Blvd. (Havemann to Majorki), Majorki Place (Irmscher to Eaglebrooke Blvd.), Eaglebrooke Parkway (Eaglebrooke Blvd east), Eaglebrooke Blvd. (Wayne to Eaglebrooke Pkwy), Linden St. (Wayne to Buckeye), Willow St. (Linden to Johnson), Maple St. (Linden to Johnson), Spruce St. (Buckeye to Maple), Ash St. & Logan St. (Main to Market), Hemlock St. (Buckeye to Willow), County Rd. (Market to Livingston incl. alleyway), Armstrong St. (Livingston to Wayne), Lilac St. (Holly to Myers), Riley St. (Market to Wayne), Deford St. (Wayne to Hierholzer), Cron St. (Deford to Mackinaw), Mercer St. (Echo to Murlin), Pine St. (Elm to Murlin), and South St. (Echo to Vining),

2020 ODOT Resurfacing Project (N. Main St.)

The Ohio Department of Transportation (ODOT) has contracted with The Shelly Co. to resurface N. Main St. from Fulton St. to the northern City Limits.  This project has a June 30th completion date and a contract bid price of $493,173.00.

2020 (ODOT) West Market Street Reconstruction Project

ODOT accepted bids for this project Thursday 1/23/2020.  The Engineer’s Estimate for this project was #1,718,000.00.  The apparent low bidder was Milcon Concrete Inc. from Troy, Ohio with a bid of $1,676,869.00.  The 2nd low bidder was Eclipse Co. LLC from Chagrin Falls, Ohio with a bid of $1,725,418.80.  This project has a completion date of 9/30/2020.

The natural gas lines in the area of this project must be lowered before this project can start.  Dominion Energy is currently preparing this project for bids.  Dominion is expected to have their work on this project completed by March 1, 2020.